Mumbai Local Mega Block: Train Services to Remain Disrupted for 35 Days, Check Latest Update

Mumbai local train services on the western line will remain disrupted for a period of 35 days because of a mega block. Here's all you need to know...

Reported by: Digital Desk
Follow: Google News Icon
×

Share


Mumbai Local Mega Block | Image: Instagram

Mumbai: The local train services in Mumbai will remain affected on the western line between Goregaon and Kandivali stations.

Those travelling by Mumbai Local, are expected to face disruptions for the next 35 days starting on the intervening night of August 27-28.

Mumbai Local Mega Block: Train Services Disrupted for 35 Days

Suburban commuters in Mumbai are likely to face inconvenience as Western Railway will operate some mega blocks on weekends between Goregaon and Kandivali stations in a 35-day period starting from August 27 to complete the 4.5 kilometre 6th line.

In a release issued on Monday, Western Railway said five 10-hour long mega blocks will be undertaken on weekends between August 27 to October 6, so as to cause minimal inconvenience to passengers.

"The work is scheduled to be completed within 35 days but no work will be undertaken from September 11 to 17 due to Ganpati festival," WR general manager Ashok Kumar Misra said.

"As there is no space to lay the 6th line on the east side of Malad station, a new line will be laid on the west side and all the existing 5 lines will be shifted to the west side through cut and connection," he said.

Western Railway Warns of Delays and Cancellations

Due to this work, a few long distance trains will be regulated by 15 to 20 minutes, while suburban services will also be affected as 100-140 services will be cancelled on an average and around 40 services will be short-terminated on weekends, the release said.

"WR has scheduled to carry out the work during the night hours so as to cause minimal disruptions on weekdays. Trains running from Bandra Terminus will be regulated by 40-45 minutes on September 28-29 and October 5-6 when non-interlocking work will be undertaken on the 5th line between Goregaon and Kandivali," it said.

While the 5th line between Bandra Terminus is commissioned, the 6th line is operation between Khar and Goregaon, while the current work is to extend the latter from Goregaon to Kandivali, officials said.

"After completion of this work, the 6th line will be extended to Borivali. It will provide a dedicated corridor for long-distance trains. Commuters will be benefited due to enhanced capacity easing congestion and improving punctuality," the official said.

(Inputs from PTI)